| AD Number | 95-05-02 | Status | Active |
| Effective Date | April 13, 1995 | Issue Date | Not specified |
| Docket Number | 94-NM-136-AD | Amendment | 39-9169 |
| Product Type | ["Aircraft"] | Product Subtype | ["Large Airplane"] |
| CFR Part | --- - Part 39 [60 FR 13621 NO. 49 3/14/95] | CFR Section | N/A |
| Citation | This information is not available. | ||
| Manufacturer(s) | Airbus SAS |
| Model(s) | A300 B4-103 A300 B4-203 A300 B4-2C A300 B4-601 A300 B4-603 A300 B4-620 A300 B4-622R |
This amendment adopts a new airworthiness directive (AD), applicable to certain Airbus Model A300 and A300-600 series airplanes, that requires modification of the fuel tank jettison system. This amendment is prompted by a quality survey which revealed that the electrical bonding of the fuel jettison system has insufficient protection from a lightning strike. The actions specified by this AD are intended to prevent electrical arcing and resultant fire in the event of a lightning strike.
Final rule.
95-05-02 AIRBUS INDUSTRIE: Amendment 39-9169. Docket 94-NM-136-AD.
Applicability: Model A300 B4-2C, B4-103, and B4-203 series airplanes on which Airbus Modification 0013 has been installed; and Model A300-600 B4-620, B4-622, B4-603, and B4-601 series airplanes on which Airbus Modification 4607 has not been installed; certificated in any category.
NOTE 1: This AD applies to each airplane identified in the preceding applicability provision, regardless of whether it has been modified, altered, or repaired in the area subject to the requirements of this AD. For airplanes that have been modified, altered, or repaired so that the performance of the requirements of this AD is affected, the owner/operator must use the authority provided in paragraph (b) to request approval from the FAA. This approval may address either no action, if the current configuration eliminates the unsafe condition; or different actions necessary to address the unsafe condition described in this AD.Such a request should include an assessment of the effect of the changed configuration on the unsafe condition addressed by this AD. In no case does the presence of any modification, alteration, or repair remove any airplane from the applicability of this AD.
Compliance: Required as indicated, unless accomplished previously.
To prevent electrical arcing and resultant fire in the event of a lightning strike, accomplish the following:
(a) Within 6 months after the effective date of this AD, modify the fuel tank jettison system in accordance with Airbus Alert Service Bulletin A300-28A065, Revision 1, dated February 14, 1994 (for Model A300 series airplanes), or Airbus Alert Service Bulletin A300-28A6033, Revision 1, dated February 14, 1994 (for Model A300-600 series airplanes); as applicable.
(b) An alternative method of compliance or adjustment of the compliance time that provides an acceptable level of safety may be used if approved by the Manager, StandardizationBranch, ANM-113, FAA, Transport Airplane Directorate. Operators shall submit their requests through an appropriate FAA Principal Maintenance Inspector, who may add comments and then send it to the Manager, Standardization Branch, ANM-113.
NOTE 2: Information concerning the existence of approved alternative methods of compliance with this AD, if any, may be obtained from the Standardization Branch, ANM-113.
(c) Special flight permits may be issued in accordance with sections 21.197 and 21.199 of the Federal Aviation Regulations (14 CFR 21.197 and 21.199) to operate the airplane to a location where the requirements of this AD can be accomplished.
(d) The modification shall be done in accordance with the following Airbus Industrie service bulletins, as applicable, which contain the specified effective pages:
Service Bulletin
Referenced and Date
Page Number
Revision Level
Shown on Page
Date
Shown on Page
A300-28A065,
Revision 1,
February 14, 1994
1-151
February 14, 1994
A300-28A6033,
Revision 1,
February 14, 1994
1-3, 5-14
4
1
Original
February 14, 1994
April 21, 1993
This incorporation by reference was approved by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. Copies may be obtained from Airbus Industrie, 1 Rond Point Maurice Bellonte, 31707 Blagnac Cedex, France. Copies may be inspected at the FAA, Transport Airplane Directorate, 1601 Lind Avenue, SW., Renton, Washington; or at the Office of the Federal Register, 800 North Capitol Street, NW., suite 700, Washington, DC.
(e) This amendment becomes effective on April 13, 1995.
A proposal to amend part 39 of the Federal Aviation Regulations (14 CFR part 39) to include an airworthiness directive (AD) that is applicable to certain Airbus Model A300 and A300-600 series airplanes was published in the Federal Register on November 16, 1994 (59 FR 59178). That action proposed to require modification of the fuel tank jettison system.
Interested persons have been afforded an opportunity to participate in the making of this amendment. Due consideration has been given to the two comments received.
Both commenters support the proposed rule.
As a result of recent communications with the Air Transport Association (ATA) of America, the FAA has learned that, in general, some operators may misunderstand the legal effect of AD's on airplanes that are identified in the applicability provision of the AD, but that have been altered or repaired in the area addressed by the AD. The FAA points out that all airplanes identified in the applicability provision of an AD are legally subject to the AD. If an airplane has been altered or repaired in the affected area in such a way as to affect compliance with the AD, the owner or operator is required to obtain FAA approval for an alternative method of compliance with the AD, in accordance with the paragraph of each AD that provides for such approvals. A note has been added to this final rule to clarify this long-standing requirement.
After careful review of the available data, including the comments noted above, the FAA has determined that air safety and the public interest require the adoption of the rule with the change previously described. The FAA has determined that this change will neither increase the economic burden on any operator nor increase the scope of the AD.
The FAA estimates that 34 airplanes of U.S. registry will be affected by this AD, that it will take approximately 21 work hours per airplane to accomplish the required actions, and that the average labor rate is $60 per work hour. Required parts will be supplied by the manufacturer at no cost to the operators. Based on these figures, the total cost impact of the AD on U.S. operators is estimated to be $42,840, or $1,260 per airplane.
The total cost impact figure discussed above is based on assumptions that no operator has yet accomplished any of the requirements of this AD action, and that no operator would accomplish those actions in the future if this AD were not adopted.
The regulations adopted herein will not have substantial direct effects on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. Therefore, in accordance with Executive Order 12612, it is determined that this final rule does not have sufficient federalism implications to warrant the preparation of a Federalism Assessment.
For the reasons discussed above, I certify that this action (1) is not a "significant regulatory action" under Executive Order 12866; (2) is not a "significant rule" under DOT Regulatory Policies and Procedures (44 FR 11034, February 26, 1979); and (3) will not have a significant economic impact, positive or negative, on a substantial number of small entities under the criteria of the Regulatory Flexibility Act. A final evaluation has been prepared for this action and it is contained in the Rules Docket. A copy of it may be obtained from the Rules Docket at the location provided under the caption "ADDRESSES."
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by reference, Safety.
Adoption of the Amendment
Accordingly, pursuant to the authority delegated to me by the Administrator, the Federal Aviation Administration amends part 39 of the Federal Aviation Regulations (14 CFR part 39) as follows:
PART 39 - AIRWORTHINESS DIRECTIVES
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. App. 1354(a), 1421 and 1423; 49 U.S.C. 106(g); and 14 CFR 11.89.
39.13 - [Amended]
2. Section 39.13 is amended by adding the following new airworthiness directive:
The service information referenced in this AD may be obtained from Airbus Industrie, 1 Rond Point Maurice Bellonte, 31707 Blagnac Cedex, France. This information may be examined at the Federal Aviation Administration (FAA), Transport Airplane Directorate, Rules Docket, 1601 Lind Avenue, SW., Renton, Washington; or at the Office of the Federal Register, 800 North Capitol Street, NW., suite 700, Washington, DC.
Stephen Slotte, Aerospace Engineer, Standardization Branch, ANM-113, FAA, Transport Airplane Directorate, 1601 Lind Avenue, SW., Renton, Washington 98055-4056; telephone (206) 227-2797; fax (206) 227-1320.