Discussion \n\n\n\tWe issued a notice of proposed rulemaking (NPRM) to amend 14 CFR part 39 by adding an AD that would apply to certain The Boeing Company Model MD-11 and MD-11F airplanes. The NPRM published in the Federal Register on May 30, 2017 (82 FR 24597). The NPRM was prompted by fuel system reviews conducted by the manufacturer. The NPRM proposed to require a one-time inspection of the wire assemblies of the tail fuel tank transfer pumps to determine if metallic transitions are installed at the wire harness breakouts, and corrective actions if necessary. We are issuing this AD to detect and correct potential ignition sources inside the tail fuel tank, \n\n((Page 217)) \n\nwhich, in combination with flammable vapors, could result in a fuel tank fire or explosion, and consequent loss of the airplane. \n\nComments \n\n\n\tWe gave the public the opportunity to participate in developing this final rule. The following presents the comments received on theNPRM and the FAA's response to each comment. \n\nSupportive Comment \n\n\n\tThe Air Line Pilots Association International stated that it agreed with the intent of the NPRM. \n\nRequest To Clarify the Description of the Unsafe Condition \n\n\n\tBoeing asked that we clarify the description of the unsafe condition identified in paragraph (e) of the proposed AD to add the potential of fuel starvation as the end-level effect. Boeing stated that referenced service information specifies that the unsafe condition could result in engine fuel starvation. \n\tWe agree that damaged wires could result in fuel starvation as a potential unsafe condition. However, we have no SFAR88 analysis or service difficulty reports associated with the loss of system functions or fuel starvation from the chafed or damaged wires identified in this AD. We do have previous Special Federal Aviation Regulation 88 (SFAR88) ADs for wire harnesses in the same area that were issued to prevent wire chafing and potential ignition sources inside the fuel tank. The actions required by this AD are intended primarily to reduce the risk of other incidents of wires chafing and subsequent fuel tank fire or explosion. Therefore, we have made no change to this AD in this regard. \n\nRequest To Change Certain Estimates in Costs of Compliance Section \n\n\n\tFedEx asked that the work-hours under the On-Condition Costs for the replacement be increased from 16 to 100. FedEx stated that the replacement cost specifies 16 work-hours, but noted that replacement of only one affected part will actually take about 100 hours. FedEx added that 100 work-hours is only for one damaged wire assembly. \n\tUnited Parcel Service (UPS) asked that the work-hours under the On- Condition Costs for the replacement be increased from 16 to 244. UPS stated that it has previously replaced this wire harness and it required 244 work hours to complete the replacement. UPS also asked that the cost for parts for the repair be added. UPS stated that ithas sourced the materials and the cost is $1,680 per airplane (or $168 per transition location). \n\tWe agree to revise the estimated on-condition work-hours. When issuing a service bulletin, Boeing estimates work-hours under expected conditions for direct labor only. As operators implement the service bulletin, they may find the actual work-hours are higher or lower than estimated. We have updated the Costs of Compliance section of this AD to reflect between 100 and 244 work-hours. We have also included the parts cost estimate provided for repairs. \n\nRequest To Add Information Notice To Service Information Citation \n\n\n\tFedEx asked that Boeing Alert Service Bulletin MD11-28A150 IN 02, dated February 24, 2017, be added to the service information cited in paragraph (g) of the proposed AD. FedEx stated that the one-time inspection and corrective actions in paragraph (g) specify performing a detailed inspection in accordance with the Accomplishment Instructions of Boeing Alert ServiceBulletin MD11-28A150, dated October 6, 2016. FedEx added that since the referenced service information was issued, Boeing released an information notice (IN 02) with part numbers for three new wire assembly kits. \n\tWe disagree with the commenter's request. Boeing Alert Service Bulletin MD11-28A150 IN 02, dated February 24, 2017, provides updated kit information for the operators. The individual wire assembly part numbers in the new kits are the same wire assembly part numbers needed for the replacement required by this AD as specified in the figures in Part 3 of the Accomplishment Instructions of Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016. Since this AD only requires the replacement of certain individual wire assembly part numbers and not the kit part numbers that consist of the individual wire assembly part numbers, we have made no change to this AD in this regard. \n\nRequest To Clarify Paragraph (h) of the Proposed AD \n\n\n\tFedEx and UPS requested that we clarify the actions specified in paragraph (h) of the proposed AD. FedEx stated that paragraph (h) of the proposed AD provides information to perform different tests than those listed in steps 1.f, 1.g., and 1.h. of Part 4 of the Accomplishment Instructions of Boeing Alert Service Bulletin MD11- 28A150, dated October 6, 2016. FedEx stated it is not clear if the required test after rework is in accordance with steps 1.a. through 1.j. of Part 4 of Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016, or per the actions specified in (h)(1), (h)(2), and (h)(3) of this AD only. FedEx and UPS also stated that the proposed AD should require test procedures only for the section that Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016, is addressing and not all the systems associated with wire assemblies AJS9013 and AJS9014. FedEx and UPS also noted that the airplane maintenance manual (AMM) references in paragraphs (h)(1) and (h)(2) of the proposed AD are incorrect (AMM28-28-01 should be AMM 28-08-01; AMM 26-21-02 should be AMM 28-21-02). \n\tWe agree to clarify which actions are required by this AD. Steps 1.f, 1.g., and 1.h. of Part 4 of the Accomplishment Instructions of Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016, are required for compliance (RC) after any rework is done and only address the system affected by this AD. The other steps identified as ''RC exempt'' as specified in Part 4 of the Accomplishment Instructions of Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016, are not a part of the requirements of this AD. \n\tThe intent of paragraph (h) of the proposed AD was to specify the corrective action for RC tests. Steps 1.f, 1.g., and 1.h. of Part 4 of the Accomplishment Instructions of Boeing Alert Service Bulletin MD11- 28A150, dated October 6, 2016, specify to accomplish tests but the steps do not specify corrective actions if the tests fail. To clarify that the tests themselves are not exceptions to BoeingAlert Service Bulletin MD11-28A150, dated October 6, 2016, we have removed paragraph (h) of the proposed AD and included the corrective action statement for the tests in paragraph (g) of this AD. \n\tWe acknowledge that the AMM references in paragraphs (h)(1) and (h)(2) of the proposed AD were incorrect and note that the AMM references for the tests are identified correctly in Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016. \n\nConclusion \n\n\n\tWe reviewed the relevant data, considered the comments received, and determined that air safety and the public interest require adopting this final rule with the changes described previously and minor editorial changes. We have determined that these minor changes: \n\tAre consistent with the intent that was proposed in the NPRM for correcting the unsafe condition; and \n\n((Page 218)) \n\n\n\tDo not add any additional burden upon the public than was already proposed in the NPRM. \n\tWe also determined that these changes will notincrease the economic burden on any operator or increase the scope of this final rule. \n\nRelated Service Information Under 1 CFR Part 51 \n\n\n\tWe reviewed Boeing Alert Service Bulletin MD11-28A150, dated October 6, 2016. The service information describes procedures for a one-time detailed inspection of the wire assemblies of the tail fuel tank transfer pumps to determine if metallic transitions are installed at the wire harness breakouts, and corrective actions that include repair and replacement of the wire assembly. This service information is reasonably available because the interested parties have access to it through their normal course of business or by the means identified in the ADDRESSES section. \n\nCosts of Compliance \n\n\n\tWe estimate that this AD affects 110 airplanes of U.S. registry. We estimate the following costs to comply with this AD: \n\n\n\tEstimated Costs ---------------------------------------------------------------------------------------------------------------- \n\tCost per Cost on U.S. \n\tAction Labor cost Parts cost product operators ---------------------------------------------------------------------------------------------------------------- Inspection........................ 4 work-hours x $85 per $0 $340 $37,400 \n\thour = $340. ---------------------------------------------------------------------------------------------------------------- \n\n\n\tWe estimate the following costs to do any necessary repairs/ replacements that will be required based on the results of the inspection. We have no way of determining the number of aircraft that might need these repairs/replacements: \n\n\n\tOn-condition Costs ---------------------------------------------------------------------------------------------------------------- \n\tAction Labor cost Parts cost Cost per product ---------------------------------------------------------------------------------------------------------------- Repair............................ 9 work-hours x $85 per Up to $1,680......... Up to $2,445. \n\thour = $765. Replacement....................... Between 100 and 244 work- $57,526.............. Between $66,026 and \n\thours x $85 per hour = $78,266. \n\tbetween $8,500 and \n\t$20,740. ---------------------------------------------------------------------------------------------------------------- \n\nAuthority for This Rulemaking \n\n\n\tTitle 49 of the United States Code specifies the FAA's authority to issue rules on aviation safety. Subtitle I, section 106, describes the authority of the FAA Administrator. Subtitle VII: Aviation Programs, describes in more detail the scope of the Agency's authority. \n\tWe are issuing this rulemaking under the authority described in Subtitle VII, Part A, Subpart III, Section 44701: ''General requirements.'' Under that section, Congress charges the FAA with promoting safe flight of civil aircraft in air commerce by prescribing regulations for practices, methods, and procedures the Administrator finds necessary for safety in air commerce. This regulation is within the scope of that authority because it addresses an unsafe condition that is likely to exist or develop on products identified in this rulemaking action. \n\tThis AD is issued in accordance with authority delegated by the Executive Director, Aircraft Certification Service, as authorized by FAA Order 8000.51C. In accordance with that order, issuance of ADs is normally a function of the Compliance and Airworthiness Division, but during this transition period, the Executive Director has delegated the authority to issue ADs applicable to transport category airplanes to the Director of the System Oversight Division. \n\nRegulatory Findings \n\n\n\tThis AD will not have federalism implications under Executive Order 13132. This AD will not have a substantial direct effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. \n\tFor the reasons discussed above, I certify that this AD: \n\t(1) Is not a ''significant regulatory action'' under Executive Order 12866, \n\t(2) Is not a ''significant rule'' under DOT Regulatory Policies and Procedures (44 FR 11034, February 26, 1979), \n\t(3) Will not affect intrastate aviation in Alaska, and \n\t(4) Will not have a significant economic impact, positive or negative, on a substantial number of small entities under the criteria of the Regulatory Flexibility Act. \n\nList of Subjects in 14 CFR Part 39 \n\n\n\tAir transportation, Aircraft, Aviation safety, Incorporation by reference, Safety.