2010-10-18 Bombardier, Inc.: Amendment 39-16297. Docket No. FAA- 2010-0475; Directorate Identifier 2010-NM-083-AD.
Effective Date
(a) This airworthiness directive (AD) becomes effective June 1, 2010.
Affected ADs
(b) None.
Applicability
(c) This AD applies to Bombardier, Inc. Model BD-100-1A10 (Challenger 300) airplanes, having serial numbers (S/Ns) 20001 through 20274 inclusive, certificated in any category.
Note 1: This AD requires revisions to certain operator maintenance documents to include new inspections. Compliance with these inspections is required by 14 CFR 91.403(c). For airplanes that have been previously modified, altered, or repaired in the areas addressed by these inspections, the operator may not be able to accomplish the inspections described in the revisions. In this situation, to comply with 14 CFR 91.403(c), the operator must request approval for an alternative method of compliance according to paragraph (l) of this AD. The requestshould include a description of changes to the required inspections that will ensure the continued operational safety of the airplane.
Subject
(d) Air Transport Association (ATA) of America Code 21 and 25: Air conditioning and Equipment/Furnishings, respectively.
Reason
(e) The mandatory continued airworthiness information (MCAI) states:
Investigation of a recent high altitude loss of cabin pressurization on a BD-100-1A10 aircraft determined that it was caused by a partial blockage of a safety valve cabin pressure- sensing port, in conjunction with a dormant failure/leakage of the safety valve manometric capsule. The blockage, caused by accumulation of lint/dust on the grid of the port plug, did not allow sufficient airflow through the cabin pressure-sensing port to compensate for the rate of leakage from the manometric capsule, resulting in the opening of the safety valve. It was also determined that failure of the manometric capsule alone would not result in the opening of the safety valve.
This directive mandates a revision of the maintenance schedule, the [repetitive] cleaning of the safety valves, the removal of material from the area surrounding the safety valves and the modification of the safety valves with a gridless cabin pressure- sensing port plug.
The unsafe condition is possible loss of cabin pressure caused by the opening of the safety valve. The required actions also include a detailed visual inspection of the safety valves and surrounding areas for discrepant material (e.g., foreign material surrounding the safety valves, room temperature vulcanizing (RTV) sealant on safety valves, RTV excess on the bulkhead, tape near the safety valve opening, and, on certain airplanes, insulation near the safety valve opening, and foam in the area surrounding the safety valves), and for contamination found in the safety valve pressure ports. If contamination is found on the safety valve pressure ports, a detailed visual inspection forthe presence of RTV on the outside and inside diameter of the pressure sensing port conduit is required. If discrepant materials are found, removing discrepant material, cleaning the surfaces of the valves, and securing insulation are required, as applicable. If the presence of RTV is detected, cleaning the surfaces of the valves and installing a new safety valve are required, as applicable.
Compliance
(f) You are responsible for having the actions required by this AD performed within the compliance times specified, unless the actions have already been done.
Actions
(g) For all airplanes: Within 30 days after the effective date of this AD, revise the Airworthiness Limitations section of the Instructions for Continued Airworthiness by incorporating Tasks 21- 31-09-101 and 21-31-09-102 in the Bombardier Temporary Revision (TR) 5-2-53, dated October 1, 2009, to Section 5-10-40, "Certification Maintenance Requirements,'' in Part 2 of Chapter 5 of Bombardier Challenger 300 BD-100 Time Limits/Maintenance Checks.
(1) For the new tasks identified in Bombardier TR 5-2-53, dated October 1, 2009: For airplanes identified in the "Phase-in'' section of Bombardier TR 5-2-53, dated October 1, 2009, the initial compliance with the new tasks must be carried out in accordance with the phase-in schedule detailed in Bombardier TR 5-2-53, dated October 1, 2009, except where that TR specifies a compliance time from the date of the TR, this AD requires compliance within the specified time after the effective date of this AD. Thereafter, except as provided by paragraph (l)(1) of this AD, no alternative to the task intervals may be used.
(2) When information in Bombardier TR 5-2-53, dated October 1, 2009, has been included in the general revisions of the applicable Airworthiness Limitations section, that TR may be removed from that Airworthiness Limitations section of the Instructions for Continued Airworthiness.
(h) For airplanes having S/Ns 20003 through 20173inclusive, 20176, and 20177: Within 50 flight hours after the effective date of this AD, do a detailed visual inspection of the safety valves and surrounding areas for discrepant material (e.g., foreign material surrounding the safety valves, room temperature vulcanizing (RTV) sealant on safety valves, RTV excess on the bulkhead, tape near the safety valve opening, and, on certain airplanes, insulation near the safety valve opening, and foam in the area surrounding the safety valves) and a detailed visual inspection for contamination (e.g., RTV, dust, or lint) in the safety valve pressure ports, in accordance with the Accomplishment Instructions of Bombardier Service Bulletin 100-25-14, dated June 30, 2008 (for airplanes having S/Ns 20124, 20125, 20128, 20134, 20139, 20143, 20146, 20148 to 20173 inclusive, 20176, and 20177); or Bombardier Service Bulletin 100-25-21, dated June 30, 2008 (for airplanes having S/Ns 20003 through 20123 inclusive, 20126, 20127, 20129 to 20133 inclusive, 20135 to 20138 inclusive, 20140 to 20142 inclusive, 20144, 20145, and 20147).
(1) If any discrepant material is found during the detailed visual inspection, before further flight, remove the discrepant material, clean the surfaces of the valves, and secure the insulation, as applicable, in accordance with the Accomplishment Instructions of Bombardier Service Bulletin 100-25-14, dated June 30, 2008 (for airplanes having S/Ns 20124, 20125, 20128, 20134, 20139, 20143, 20146, 20148 to 20173 inclusive, 20176, and 20177); or Bombardier Service Bulletin 100-25-21, dated June 30, 2008 (for airplanes having S/Ns 20003 through 20123 inclusive, 20126, 20127, 20129 to 20133 inclusive, 20135 to 20138 inclusive, 20140 to 20142 inclusive, 20144, 20145, and 20147).
(2) If contamination (e.g., RTV, dust, or lint) is found on the safety valve pressure sensing ports, before further flight, do a detailed visual inspection of the outside and inside diameters of the pressure sensing port conduit for thepresence of RTV; and do the actions specified in paragraph (h)(2)(i) and (h)(2)(ii) of this AD, as applicable; in accordance with the Accomplishment Instructions of Bombardier Service Bulletin 100-25-14, dated June 30, 2008 (for airplanes having S/Ns 20124, 20125, 20128, 20134, 20139, 20143, 20146, 20148 to 20173 inclusive, 20176, and 20177); or Bombardier Service Bulletin 100-25-21, dated June 30, 2008 (for airplanes having S/Ns 20003 through 20123 inclusive, 20126, 20127, 20129 to 20133 inclusive, 20135 to 20138 inclusive, 20140 to 20142 inclusive, 20144, 20145, and 20147).
(i) If no RTV is found, clean the plug of the sensing port.
(ii) If any RTV is found, install a new safety valve.
(i) For airplanes having S/Ns 20174, 20175, 20178 through 20189 inclusive, 20191 through 20228 inclusive, 20230 through 20232 inclusive, 20235, 20237, 20238, 20241, 20244, 20247, 20249 through 20251 inclusive, 20254, 20256 and 20259: Within 50 flight hours after the effective date of this AD,clean the cabin pressure- sensing port plug in both safety valves, in accordance with Paragraph 2.B., "Part A--Modification--Cleaning,'' of the Accomplishment Instructions of Bombardier Service Bulletin A100-21- 08, dated June 18, 2009.
(j) For airplanes having S/Ns 20003 through 20189 inclusive, 20191 through 20228 inclusive, 20230 through 20232 inclusive, 20235, 20237, 20238, 20241, 20244, 20247, 20249 through 20251 inclusive, 20254, 20256, and 20259: Within 50 flight hours after the effective date of this AD, clean the cabin pressure-sensing port plug in both safety valves, in accordance with Paragraph 2.B., "Part A-- Modification--Cleaning,'' of the Accomplishment Instructions of Bombardier Service Bulletin A100-21-08, dated June 18, 2009. Repeat the cleaning thereafter at intervals not to exceed 50 flight hours until the actions specified by paragraph (k) of this AD are completed.
(k) For airplanes, having S/Ns 20003 through 20189 inclusive, 20191 through 20228 inclusive, 20230 through 20232 inclusive, 20235, 20237, 20238, 20241, 20244, 20247, 20249 through 20251 inclusive, 20254, 20256, and 20259: Replacing the cabin pressure-sensing port plug having part number (P/N) 2844-060 in both safety valves with a new gridless plug having P/N 2844-19 and re-identifying the safety valves, in accordance with Paragraph 2.C., "Part B--Modification-- Replacement,'' of the Accomplishment Instructions of Bombardier Service Bulletin A100-21-08, dated June 18, 2009, terminates the repetitive cleanings required by paragraph (j) of this AD.
FAA AD Differences
Note 2: This AD differs from the MCAI and/or service information as follows: This AD does not require the replacement of the safety valve cabin pressure-sensing port plugs and the re-identification of the safety valves required in Part V of MCAI Canadian Airworthiness Directive CF-2010-06, dated February 24, 2010. The planned compliance times for these actions would not allow enough time to provide notice andopportunity for prior public comment on the merits of those actions. Therefore, we are considering further rulemaking to address these issues.
Other FAA AD Provisions
(l) The following provisions also apply to this AD:
(1) Alternative Methods of Compliance (AMOCs): The Manager, New York Aircraft Certification Office, ANE-170, FAA, has the authority to approve AMOCs for this AD, if requested using the procedures found in 14 CFR 39.19. Send information to ATTN: Program Manager, Continuing Operational Safety, FAA, New York ACO, 1600 Stewart Avenue, Suite 410, Westbury, New York 11590; telephone 516-228-7300; fax 516-794-5531. Before using any approved AMOC on any airplane to which the AMOC applies, notify your principal maintenance inspector (PMI) or principal avionics inspector (PAI), as appropriate, or lacking a principal inspector, your local Flight Standards District Office. The AMOC approval letter must specifically reference this AD.
(2) Airworthy Product: For any requirement in this AD to obtain corrective actions from a manufacturer or other source, use these actions if they are FAA-approved. Corrective actions are considered FAA-approved if they are approved by the State of Design Authority (or their delegated agent). You are required to ensure the product is airworthy before it is returned to service.
(3) Reporting Requirements: For any reporting requirement in this AD, under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.), the Office of Management and Budget (OMB) has approved the information collection requirements and has assigned OMB Control Number 2120-0056.
Related Information
(m) Refer to MCAI Canadian Airworthiness Directive CF-2010-06, dated February 24, 2010; and the service information specified in Table 1 of this AD; as applicable; for related information.
Table 1--Service Information
Document
Date
Bombardier Service Bulletin A100-21-08
June 18, 2009
Bombardier Service Bulletin 100-25-14
June 30, 2008
Bombardier Service Bulletin 100-25-21
June 30, 2008
Bombardier Temporary Revision 5-2-53, dated October 1, 2009, to Section 5-10-40, Certification Maintenance Requirements, in Part 2 of Chapter 5 of Bombardier Challenger 300 BD-100 Time Limits/Maintenance Checks.
October 1, 2009
Material Incorporated by Reference
(n) You must use the service information contained in Table 2 of this AD to do the actions required by this AD, unless the AD specifies otherwise.
Table 2--Material Incorporated by Reference
Document
Date
Bombardier Service Bulletin A100-21-08
June 18, 2009
Bombardier Service Bulletin 100-25-14
June 30, 2008
Bombardier Service Bulletin 100-25-21
June 30, 2008
Bombardier Temporary Revision 5-2-53, dated October 1, 2009, to Section 5-10-40, Certification Maintenance Requirements, in Part 2 of Chapter 5 of Bombardier Challenger 300 BD-100 Time Limits/Maintenance Checks.
October 1, 2009
(1) The Director of the Federal Register approved the incorporation by reference of this service information under 5 U.S.C. 552(a) and 1 CFR part 51.
(2) For service information identified in this AD, contact Bombardier, Inc., 400 C[ocirc]te-Vertu Road West, Dorval, Qu[eacute]bec H4S 1Y9, Canada; telephone 514-855-5000; fax 514-855- 7401; e-mail thd.crj@aero.bombardier.com; Internet http:// www.bombardier.com.
(3) You may review copies of the service information at the FAA, Transport Airplane Directorate, 1601 Lind Avenue, SW., Renton, Washington. For information on the availability of this material at the FAA, call 425-227-1221.
(4) You may also review copies of the service information that is incorporated by reference at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to: http:// www.archives.gov/federal_register/code_of_federal_regulations/ ibr_locations.html.