The FAA proposed to amend 14 CFR part 39 with a proposed AD. The proposed AD applies to GE CF6-80C2 turbofan engines with certain P/N HPT S2 NGVs installed. We published the proposed AD in the Federal Register on November 18, 2003 (68 FR 65000). That action proposed to require flex borescope inspections of certain P/N HPT S2 NGVs installed in CF6-80C2A1, -80C2A2, -80C2A3, -80C2A5, - 80C2A5F, -80C2A8, -80C2B1, -80C2B1F, -80C2B2, -80C2B2F, -80C2B4, - 80C2B4F, -80C2B5F, -80C2B6, -80C2B6F, -80C2B6FA, -80C2B7F, and -80C2D1F turbofan engines.
Examining the AD Docket: You may examine the AD Docket (including any comments and service information), by appointment, between 8 a.m. and 4:30 p.m., Monday through Friday, except Federal holidays. See ADDRESSES for the location.
Comments
We provided the public the opportunity to participate in the development of this AD. We have considered the comments received.
Requests To Limit the Required InspectionsSeven commenters ask that we limit the inspections required by the proposed AD to those parts listed in paragraph 1.C.(6) of GE Service Bulletin (SB) No. CF6-80C2 S/B 72-0952, Revision 6, dated May 5, 2003, and that we revise Table 1 of the proposed AD to clarify the affected parts. The commenters state that those parts are the population recommended by the Manufacturer. We agree. We revised the applicability paragraph and Table 1 of the final rule for consistency with GE SB No. CF6-80C2 S/B 72-0952, Revision 6, dated May 5, 2003. We also clarified the applicability of certain P/Ns in Table 1 by adding, "Insert, P/N 1957M40G01 or P/N 1957M40G02, was installed during modification or repair," to those parts.
Six commenters ask that we limit the inspections required by the proposed AD to areas of critical stress such as the leading edge and outer fillet areas of the HPT nozzle airfoil as specified in Paragraph 3.B.(3) of GE SB No. CF6-80C2 S/B 72-0952, Revision 6, dated May 5, 2003. The commenters feel that the proposed AD requires inspecting HPT blades as well as the nozzles, but that the cracking of the nozzles is the primary cause of failure of the HPT blade. The commenters feel that the proposed AD requires inspecting noncritical areas of nozzles. We agree. We revised paragraph (f) of the final rule to state "Flex- borescope inspect the NGVs following paragraphs 3.B.(3) through 3.B.(5) of the * * *." We also deleted paragraphs (f)(1) through (f)(3)(ii) because they applied to HPT S2 NGVs that have not been repaired.
Requests for a Drawdown Allowance and Credit for Inspections Already Done
Five commenters ask that we provide an appropriate drawdown allowance for engines that have exceeded the threshold for the initial inspection, or provide credit for inspections that have already been done. The commenters feel that some engines might have already exceeded the initial limits. We agree that credit should be given for inspections that were performed before the effective date of the final rule, however, the proposed AD already provides for that credit by stating in paragraph (e) of the proposed AD "You are responsible for having the actions required by this AD performed within the compliance times specified, unless the actions have already been done". We changed paragraph (f)(2) of the final rule to state "For engines listed in paragraphs (f)(1)(i) and (f)(1)(ii) of this AD that are already beyond the initial inspection thresholds, inspect at or before accumulating an additional 200 CSO after the effective date of this AD."
Request To Add CF6-80C2B8F to the Applicability
Two commenters ask us to add the CF6-80C2B8F engine model to the Applicability. The commenters state that the engine model was in the SB before we issued the NPRM. We agree. We have added the CF6-80C2B8F engine model to the Applicability of the final rule.
Request To Withdraw the NPRM
Two commenters ask us to withdraw the NPRM because they do not feel there is an issue with safety of flight. One commenter states that they have not removed any engines for this cause. The other commenter states that the engine fragments that exited the engine via holes in the low pressure turbine case were small and caused only minor damage to the airplane. We do not agree. We identified an unsafe condition after an uncontained engine failure. We provided a discussion of the cause of the uncontained engine failure and how the condition could affect other engines of the same type design. We are issuing this AD to prevent future occurrences of the same unsafe condition.
Request To Change Blade Failure to Blade Separation
One commenter asks us to change "blade failure" to "blade separation." The commenter states this is consistent with using the term failure when the failure of the part is the primary cause. We agree. We have changed "blade failure" to "blade separation" in the final rule.
Request To Change CSO to CSN
One commenterasks us to state the inspection compliance times for new nozzles in paragraph (f)(2)(i) through (iii) in terms of "CSN." The commenter feels this will clarify the requirements. We agree that the change would have clarified the requirements of the original NPRM. However, based on previous comments, the final rule will apply only to repaired or modified nozzles and the paragraphs that the commenter asks us to change will not be included in the final rule.
Requests To Limit Reinspection Requirements
Two commenters ask us to limit the reinspection requirements in paragraph (g) for the outer fillet to Figure 5, sheets 1 and 2 of GE SB No. CF6-80C2 S/B 72-0952, Revision 6, dated May 5, 2003. The commenters state that those sheets are the specific inspection requirements for cracking in the outer fillet. We agree. We added "Sheets 1 and 2" to paragraph (g) of the final rule.
Requests To Change the Reinspection intervals
Several commenters ask us to change the reinspection intervals that are incorporated by reference in paragraph (g). The commenters feel that the requirement to "reinspect at the next regular S2 Blade Inspection" as stated in Figure 5 of GE SB No. CF6-80C2 S/B 72-0952, Revision 6, dated May 5, 2003, might be misleading. Although the next regular S2 Blade Inspection should coincide with 250 cycles-since-last- inspection (CSLI) for CF6-80C2D1F engines with 5.0 or more cycles per flight leg and 400 CSLI for all other engines, the lack of specific cyclic limits might cause confusion. We agree. We added new paragraphs (h), (h)(1), and (h)(2) to the final rule to define the next regular S2 Blade Inspection as cyclic limits of 250 and 400 CSLI respectively.
Request To Delete or Change the Paragraph Relating To Operation as More Than One Engine Configuration
Two commenters ask us to delete or change paragraph (h) of this AD, "Engines Operated as More than One Engine Model Configuration (Thrust Level)." Both commenters feel that we should delete paragraph (h) because the inspections are limited to repaired nozzles. One commenter also feels that we need a provision for engines that have operated at different thrust levels (i.e., reconfigured from one model to another model) before the initial inspection. We agree. We changed paragraph (i) of the final rule to require performing the initial inspection at the lowest applicable inspection threshold, and reinspection intervals associated with the current engine model configuration.
Conclusion
We have carefully reviewed the available data, including the comments received, and determined that air safety and the public interest require adopting the AD with the changes described previously. We have determined that these changes will neither increase the economic burden on any operator nor increase the scope of the AD.
Costs of Compliance
There are about 1,100 GE CF6-80C2 turbofan engines of the affected design in the worldwide fleet. We estimate that this AD will affect 300 of these engines installed on airplanes of U.S. registry. We also estimate that it will take about 2 work hours per engine to perform the inspections on engines that exhibit no damage, and therefore require no mapping of damage, and that the average labor rate is $65 per work hour. Based on these figures, we estimate the total cost of this AD to U.S. operators to be $39,000.
Regulatory Findings
We have determined that this AD will not have federalism implications under Executive Order 13132. This AD will not have a substantial direct effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government.
For the reasons discussed above, I certify that this AD:
(1) Is not a "significant regulatory action" under Executive Order 12866;
(2) Is not a "significant rule" under DOT Regulatory Policies and Procedures (44 FR 11034, February 26, 1979); and
(3) Will not have a significant economic impact, positive or negative, on a substantial number of small entities under the criteria of the Regulatory Flexibility Act.
We prepared a summary of the costs to comply with this AD and placed it in the AD Docket. You may get a copy of this summary by sending a request to us at the address listed under ADDRESSES. Include "AD Docket No. 2003-NE-43-AD" in your request.
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by reference, Safety.
Adoption of the Amendment
Accordingly, under the authority delegated to me by the Administrator, the Federal Aviation Administration amends 14 CFR part 39 as follows:
PART 39--AIRWORTHINESS DIRECTIVES
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. 106(g), 40113, 44701.
39.13 [Amended]
2. The FAA amends 39.13 by adding the following new airworthiness directive: